Bridge

Tsuen Wan Bypass – Phase I

Completed Project

The first highway project

In 1978, Dragages broke new ground with its first major Hong Kong highway project.

The dual three-lane expressway, which weaved its way through an existing busy network of roadways, required complex at grade construction work and rock excavation.

The post-tensioned concrete viaduct was poured on site and rock excavation was done by a rock splitting technique.

The completion of the new bypass successfully upgraded the road network and alleviated congestion.

Client Highways Department, Hong Kong Government
Project Construction of a curved box girder viaduct bypass
Bypass 6,000m
Construction period 1978 - 1981

Reminder: Fake purchase orders are circulating under the names of Bouygues Construction and the group’s subsidiaries. Protect yourself by carrying out the following checks as a matter of habit:

  • Look for the QR code that is present on every Bouygues Construction purchase order.
  • Check that your contact email address ends with  @bouygues-construction.com or @dragageshk.com
  • If in doubt, or if you receive a fake email, be sure to get in touch with your usual Bouygues contact or use the contact form available on this website.