Railway

Kwai Fong and Kwai Hing MTR Stations

Completed Project

As Hong Kong’s urban area continued to extend into the New Territories, new MTR stations were commissioned to link the expanding communities. The Kwai Fong and Kwai Hing station foundations and viaducts involved a design-and-build contract.

The 1,200-metre viaduct segment was designed using a continuous pre-stressed structure. The average length of each span was more than 30 metres.

Both stations were designed with the passenger concourse below an elevated platform deck.

Client MTR Corporation
Project Construction of the elevated stations and a 1,200 m viaduct
Construction period 1979 - 1980

Reminder: Fake purchase orders are circulating under the names of Bouygues Construction and the group’s subsidiaries. Protect yourself by carrying out the following checks as a matter of habit:

  • Look for the QR code that is present on every Bouygues Construction purchase order.
  • Check that your contact email address ends with  @bouygues-construction.com or @dragageshk.com
  • If in doubt, or if you receive a fake email, be sure to get in touch with your usual Bouygues contact or use the contact form available on this website.