Bridge

Kai Tak Airport Taxiway Bridge

Completed Project

Short-cut bridge alleviates congestion on busy runway

Such was Hong Kong’s popularity as a business and leisure destination, Kai Tak was, by the early 1990s, facing heavy congestion. The decision was taken to construct a bridge, providing a short-cut from the runway, thus reducing taxiing time.

To accelerate the project, Dragages began to work on the foundations while the bridge design details were still being finalised. Special requirements included a load-bearing capacity equivalent to two fully-laden Boeing 747-400Fs and a bridge platform height sufficient to allow a fireboat to pass underneath.

During the construction process, Dragages had to overcome a number of constraints. Some construction activities were strictly limited between midnight and 5:00 am and tall equipment had to be lowered rapidly to facilitate takeoff and landing of planes.

Client Civil Engineering Department, Hong Kong Government
Project Design and build a bridge
Bridge length 230m
Construction period 1992 - 1993

Reminder: Fake purchase orders are circulating under the names of Bouygues Construction and the group’s subsidiaries. Protect yourself by carrying out the following checks as a matter of habit:

  • Look for the QR code that is present on every Bouygues Construction purchase order.
  • Check that your contact email address ends with  @bouygues-construction.com or @dragageshk.com
  • If in doubt, or if you receive a fake email, be sure to get in touch with your usual Bouygues contact or use the contact form available on this website.